Review the change-control evidence
Objectives
The release manager labels every entry compliant because all six mention code or images. Review each entry as a separate claim against the control baseline; do not infer missing safeguards from another entry.
The baseline requires confidential state, approval of the exact applied plan, investigation of unauthorized drift, and replacement-based immutable updates. Reject violations using the single closest reason code; accept evidence that explicitly satisfies its claim.
Verdicts are accept or reject. Every rejection needs one reason code from: state-exposure | approval-mismatch | drift-adoption | mutable-update.
Six independent release claims
CI-1 | State download is open to all staff; generated credentials remain in the file. Terminal masking is cited as protection. CI-2 | Plan digest A was approved. New inputs produced digest B, which was applied without another review. CI-3 | A public administration rule appeared without approval. The team copied it into configuration solely to silence the comparison alert. CI-4 | The immutable-update claim relies on operators patching every running instance in place while keeping the original image label. CI-5 | The authorization claim links a reviewed source revision and saved plan digest to an independent approver and matching deployment receipt; logs show no bypass. CI-6 | The replacement claim links a scanned image digest to new healthy instances, traffic cutover, and retirement of old instances; durable data stayed external.
Checks the server runs (3)
- Every line in the fixture carries a verdict
- Accept and reject land on the right lines
- Each rejection cites a valid reason code
Check names are all you see here: the expectations that decide pass or fail, and the reference solution, stay on the server.
Step-by-step hints
The guided walkthrough, in full. It is free: no XP cost, and it does not touch the paid hint ladder or the reveal gate.
- Step 1
Read the request before the artefact
Read the baseline before judging the claims. Treat each row as a separate evidence assertion with its own scope.
- Step 2
Judge every line, including the boring ones
Account for every fixture row once, including rows that provide convincing evidence rather than a defect.
Every line in the fixture carries a verdict
- Step 3
Separate what is wrong from what is merely ugly
Compare actual operations with the baseline. A familiar artifact name cannot compensate for a contradictory operation, while explicit matching evidence should not be rejected for hypothetical omissions outside its claim.
Accept and reject land on the right lines
- Step 4
Say why, in the vocabulary the programme uses
Choose the root failure category rather than a downstream consequence. Leave the explanation field empty for a claim that meets its stated control.
Each rejection cites a valid reason code
Rules summary
XP on pass
40 bonus XP the first time every check goes green.
Paid hints
2 available. Each costs 25% of the lab XP (about 10 XP).
Reveal solution
Scores 0 XP and unlocks only after 3 check runs.
Attempt cap
60 check runs per learner. The runner warns you in the last 10.